I am not able to share the milestones, tasklists with my clients. The clients after log in only get to see the project list on top but don't get to see anything in the dashboard or in the milestones and tasklists section.
Please help.
ushak, 161 - days ago
This is because the milestones/tasklists flag would have been set as Internal instead of External. i.e Clients can view only the tasks & milestones that are set as External.
Set the milestone/tasklist flag as External, so that your project clients can view the milestones and tasks.
annes1, 161 - days ago
How do I change the name of my site? So not the project but the actual site itself? Thanks.
marinas, 150 - days ago
hi would like to know how to : 1 create project and tasks that are private (can't be seen by portal owner at least in default view) 2. how can i search for something within forums? 3. how can i move/copy tasks between projects thank you marina
uprasanna (Guest), 149 - days ago
@ annes1,
Its not possible for you to change the name of your site (portal) because the site name change can be done only from our end.
Send your existing portal URL and the newly required portal URL to support[at]zohoprojects[dot]com.
Note: No special characters allowed in the portal URL.
nana_dong, 149 - days ago
Hi. My co-workers get a message when they log in telling them they have not confirmed their login, and that their account will expire soon. Where do we confirm their login?
uprasanna (Guest), 149 - days ago
@nana_dong,
Follow the steps mentioned in the below provided URL to confirm the email address.
http://zoho.com/sso-help.html#resendconfirmation
david.sarnowski, 148 - days ago
Are there plans to make zoho project work offline? I love it, but I cannot do any work or refer to any tasks when I am on the road without an internet connection.
uprasanna, 148 - days ago
@david.sarnowski,
Thanks for your compliments. Plans of making Zoho Projects work offline is not in our road map as of now.
We will analyze this feature and consider providing the same in future, if feasible.
kuhnster, 143 - days ago
Is anyone having a problem where tasks/milestones don't appear for other members in the project team?
Thanks,
Rodney
kuhnster, 143 - days ago
My Tasks and Task Lists that do not have milestones associated with thim have gone missing.
I am not sure if it related to me changing the name of my project.
I would most appreciate any help.
Thanks,
Rodney
zohoprojects, 143 - days ago
@ kuhnster,
Select "All" option from the "View Others Tasks" drop down available on the right side in tasks & milestone page and check whether all your tasks & task lists are displayed.
If the same problem persists, send your contact number & best possible time to support[at]zohoprojects[dot]com, so that I can contact you to look into the problem you face and resolve at once.
intec_building, 123 - days ago
It must be possible to enter all data also when date and time already experied since very often information is entered after an event took place. For us it is a killer criteria.
intec_building, 123 - days ago
German language version
Language character encoding: There are many German strings, mainly German special characters (Umlaute), especially in tool-tips that are displayed incorrectly.
Also all strings, label names, ... must be checked since they are also not correct sometimes.
uprasanna, 123 - days ago
@intec_building,
As of now, it is possible to modify tasks, milestones but it is not possible to modify meetings that are expired in time.
Ability to modify meeting details in the expired time line will be analyzed and provided in future as per the priority.
Thanks for your patience until then!!!
uprasanna, 123 - days ago
@intec_building,
Sorry that German special characters are displayed incorrectly. Please send a snapshot of the same to support[at]zohoprojects[dot]com and send the proper German string, so that we can update incorrect one with the proper German string.
Looking forward to hear from you!!
johndellasala, 123 - days ago
I am having a very difficult time. I am part of the Smart Card Project. My username is JohnDellasala, and my password is 120839. For some unknown reason, I never received a confirmation of my registration, although I followed the instructions that I was given at the time that I registered. My e-mail address is jdellasala@earthlink.net. Please help me. Thanks. John
nikkimelanson, 116 - days ago
Hi,
When I delete a task within a milestone, does it remove all time, subtasks and documents associated with that task? If so, how can I close the task so that I retain that information?
Nikki
nmelanson@tnc.org
uprasanna, 115 - days ago
@ nikkimelanson,
On deleting a task, the time logged for that task will be removed from the time sheet but subtasks (i.e child task that is dependent on the task to be deleted) and documents associated with that task will not be deleted.
vastsilence, 113 - days ago
Hi,
I'd like to know if i can change my portal address to another name. I accidentally made mistake in specifying my portal name.
Cheers, Sush
uprasanna, 112 - days ago
@vastsilence,
Yes, it is possible to change the portal URL but the change can be done only from our side.
Send your existing and newly required portal URL to support[at]zohoprojects[dot]com, so that we can do the portal address change, if available.
Note: No special characters allowed in the portal URL.
markander, 111 - days ago
Can I download an entire folder or do I have to download the image files one at a time?
ayudaprojects (Guest), 111 - days ago
I am a new user. Wanting to use this with a client (free version). If it works well I will integrate it into my consulting business.
My issues: 1) I am unable to "select" a Client I have set-up. So to add a client user I had to set-up the client again. How do I delete duplicate Clients and why can't I choose a Client I have already set-up? 2) Once I have that all set-up, how do I allow the Client access to the site? 3) What do they have to do to participate? Will they be able to participate fully as a Client user or would I better served to set them up as a project user?
These three items are not discussed on the online help guide that I can find. Thanks, Melinda (ayudaprojects)
uprasanna, 109 - days ago
@ markander,
As of now, it is not possible to download the entire folder at a time. Instead you can download the image file one at a time.
vishnukiranreddy, 108 - days ago
Hi, I want to change my email address where i am receiving the mails. Could you please tell me steps about how to change it.
Thanks, Vishnu
uprasanna, 108 - days ago
@ vishnukiranreddy,
To change the email address, Login to http://accounts.zoho.com --> click 'My Email IDs' --> click 'Edit' option to the right of the email address --> update the new email address.
Once done all the emails will be received only in your new email address.
thelwall (Guest), 102 - days ago
I am trying Zoho for the first time & so I may not understand all the possibilities. However, one of the most powerful things in this type of app is the use of task dependencies. It seems I have to have got these worked out in advance and entered tasks not only in the right sequence but also with dates that make dependencies valid.
If I am right, this makes "dependencies" almost unusable. Surely I want to get tasks down as quickly as possible and then specify dependencies. If a "child" task has a start date that is before its newly specified "parent" then the child start date should automatically become the finish date of the "parent". Otherwise I have to use something like MS project to sort things out first and then enter in Zoho .. if so lets just use MSP
Also what happens if I want to add some new Milestone with new dependencies .. do I have to alter all previous stuff manually. Surely not .. it wd be a nightmare. Furthermore, if tasks overrrun, what happens to start dates of "child" tasks; they shd be re-scheduled.
What I would like to be able to do is to fill in task durations only and then the start date of the first task, set the dependencies and then all start & finish dates wd be calculated for me .. wouldn't they?
One further point re Dependencies, can Task Lists be parents & children as per tasks. This can be very useful indeed .. I realise one cd set the last task(chronologically) in a list to be the parent of the first task in another, dependent, list.
Look forward to your comments.
David
Anil Baddi (Guest), 81 - days ago
How do I ensure that PROJECT TIME VARIANCE be recorded and measured in zohoprojects ? Specifically, I would like EACH PROJECT broken down INTO TASKS. Each Task has a specific BUDGETED HOURS (BILLABLE HOURS) - WITH START DATE / FINISH DATE
When I allocate RESOURCES to work on TASKS, while filling up TIMESHEET, ACTUAL EFFORT = BILLABLE HOURS + NON-BILLABLE HOURS (variance)
Is there any way to allocate expenses to a project? Whether they be labor or materials? I would love to have a central place for people to enter their costs. Right now we send by e-mail and it is a data entry pain. Thanks! Mark
barrys, 57 - days ago
How do you see milestones for EVERY project on one screen?
barrys, 57 - days ago
How do we integrate Google Docs & Googles Apps Calendars?
joshua.chappell, 56 - days ago
To respond to Barrys' comment, click "My Home" in Zoho projects. It should display all of the milestones assigned to your account.
Now I have a question, is there a way to back-up Zoho projects to a hard drive? I've already solved the problem with Zoho Creator, but the projects post much more of a problem.
shukr (Guest), 55 - days ago
We can not see the photos of each other in the project
uprasanna, 53 - days ago
@Mark+markboylan@aol.com,
As of now, it is not possible to allocate expenses to a project and maintain the total cost of all the project members.
uprasanna, 53 - days ago
@barrys,
As of now, it's not possible for you integrate Google Docs and Google Apps in Zoho Projects.
Guest, 43 - days ago
Is importing from Microsoft project available in the free version? I can't seem to find where to do it.
uprasanna, 42 - days ago
@Guest,
Importing Microsoft Project is not possible in current version of Zoho Projects but will be available in the new version of Zoho Projects i.e Zoho Projects 2.0, which will be launched by this month end.
annelouisebrooks, 32 - days ago
I'd love to be able to establish dependencies within a project template so that they were carried into the newly created project. Is that something that may be available soon? I think your product is great, but that one last feature within the project template would make it even better!
craig (Guest), 29 - days ago
can we link two portals?
I mean I already have some tasks in a portal. but due to some work reasons, i need to perform those tasks in another portal. how can I
move those tasks from the former portal to the new one. thanks
johannesdgavnet (Guest), 25 - days ago
It would be great if there was a built-in chat function like in gmail. Then we could talk in real time while being on the platform at the same time.
J
jungbh0830, 25 - days ago
when i edit 'company name' of 'edit profile' in 'company settings' menu. 'update profile' button can't update company name column.. help .plz..
uprasanna, 22 - days ago
@craig,
You can access both the portals (if you are added to the portals) but it's not possible to move tasks from one portal to another portal.
steve.parker, 22 - days ago
Just getting started evaluating Projects. In setting dependencies, it appears there are the following limitations vs. MS Project 1) dependent task must start on the day following the preceding task, not on the same day, 2) no ability to allow duration of dependent task to overlap part of duration of preceding task, 3) time increments are limited to 1 day, not hours within a day,
I have common situations where several people must report some info and final report is dependent on receipt of all. Actually doing the report happens concurrently with the other people generating their info. Once I have it all, I can finish the report in under an hour.
Can the current Zoho Project handle this and if not, will the 2.o release this month have some or all of these abilities?
Thanks!!
mandarmehta, 20 - days ago
Can i add fields/ pick list to the task form?
Mandar
uprasanna, 14 - days ago
@mandarmehta,
All the fields in task form are fixed and its not possible to add additional fields to the task form.
uprasanna, 14 - days ago
@jungbh0830,
Sorry that the profile failed to get updated.
Currently, company & user settings are stored in our central IAM server and the setting changes will reflect after 5 minutes time. This is because of the caching method used in our IAM server.
So, please update profile and check for the changes after 5 minutes of time.
The caching method is not used in Zoho Projects 2.0 (new version of Zoho Projects) and the setting changes will be reflected immediately.
jon@japanmusicweek.com+(Guest), 12 - days ago
Please can you help?
After I fill in fields in Company Profile at http://japanmusicweek.projects.zoho.com
it says "updated successfully" but returns the previous blank/wrong settings..
jon
uprasanna, 11 - days ago
@jon,
Currently, company & user settings are stored in our central IAM server and the setting changes will reflect after 5 minutes time. This is because of the caching method used in our IAM server.
So, please update company profile and check for the changes after 5 minutes time.
Note: iSetting changes will be reflected immediately in Zoho Projects 2.0 as the caching method is not used in Zoho Projects 2.0.
sarbast, 3 - days ago
i do not know the space fo information collection and where i get all comment of the project
thanks for your help.
markmosys, 3 - days ago
Resource Management is a large part of any Project, how is this best acheived...i.e as in MSProject you can see available time, over allocation etc.
To whom it may concern:
How to I close an entire project and make sure all the files and links are deleted for ever? Do I need to delete each file one at a time???
Thanks
Erick
Visit the URL mentioned below to know about clearing the project data and deleting the entire project.
http://zohoprojects.wiki.zoho.com/How-To---Project-Setup.html
I am not able to share the milestones, tasklists with my clients. The clients after log in only get to see the project list on top but don't get to see anything in the dashboard or in the milestones and tasklists section.
Please help.
This is because the milestones/tasklists flag would have been set as Internal instead of External. i.e Clients can view only the tasks & milestones that are set as External.
Set the milestone/tasklist flag as External, so that your project clients can view the milestones and tasks.
How do I change the name of my site? So not the project but the actual site itself? Thanks.
hi would like to know how to :
1 create project and tasks that are private (can't be seen by portal owner at least in default view)
2. how can i search for something within forums?
3. how can i move/copy tasks between projects
thank you
marina
@ annes1,
Its not possible for you to change the name of your site (portal) because the site name change can be done only from our end.
Send your existing portal URL and the newly required portal URL to support[at]zohoprojects[dot]com.
Note: No special characters allowed in the portal URL.
Hi. My co-workers get a message when they log in telling them they have not confirmed their login, and that their account will expire soon. Where do we confirm their login?
@nana_dong,
Follow the steps mentioned in the below provided URL to confirm the email address.
http://zoho.com/sso-help.html#resendconfirmation
Are there plans to make zoho project work offline? I love it, but I cannot do any work or refer to any tasks when I am on the road without an internet connection.
@david.sarnowski,
Thanks for your compliments. Plans of making Zoho Projects work offline is not in our road map as of now.
We will analyze this feature and consider providing the same in future, if feasible.
Is anyone having a problem where tasks/milestones don't appear for other members in the project team?
Thanks,
Rodney
My Tasks and Task Lists that do not have milestones associated with thim have gone missing.
I am not sure if it related to me changing the name of my project.
I would most appreciate any help.
Thanks,
Rodney
@ kuhnster,
Select "All" option from the "View Others Tasks" drop down available on the right side in tasks & milestone page and check whether all your tasks & task lists are displayed.
If the same problem persists, send your contact number & best possible time to support[at]zohoprojects[dot]com, so that I can contact you to look into the problem you face and resolve at once.
It must be possible to enter all data also when date and time already experied since very often information is entered after an event took place. For us it is a killer criteria.
German language version
Language character encoding: There are many German strings, mainly German special characters (Umlaute), especially in tool-tips that are displayed incorrectly.
Also all strings, label names, ... must be checked since they are also not correct sometimes.
@intec_building,
As of now, it is possible to modify tasks, milestones but it is not possible to modify meetings that are expired in time.
Ability to modify meeting details in the expired time line will be analyzed and provided in future as per the priority.
Thanks for your patience until then!!!
@intec_building,
Sorry that German special characters are displayed incorrectly. Please send a snapshot of the same to support[at]zohoprojects[dot]com and send the proper German string, so that we can update incorrect one with the proper German string.
Looking forward to hear from you!!
I am having a very difficult time. I am part of the Smart Card Project. My username is JohnDellasala, and my password is 120839. For some unknown reason, I never received a confirmation of my registration, although I followed the instructions that I was given at the time that I registered. My e-mail address is jdellasala@earthlink.net.
Please help me.
Thanks.
John
Hi,
When I delete a task within a milestone, does it remove all time, subtasks and documents associated with that task? If so, how can I close the task so that I retain that information?
Nikki
nmelanson@tnc.org
@ nikkimelanson,
On deleting a task, the time logged for that task will be removed from the time sheet but subtasks (i.e child task that is dependent on the task to be deleted) and documents associated with that task will not be deleted.
Hi,
I'd like to know if i can change my portal address to another name. I accidentally made mistake in specifying my portal name.
Cheers,
Sush
@vastsilence,
Yes, it is possible to change the portal URL but the change can be done only from our side.
Send your existing and newly required portal URL to support[at]zohoprojects[dot]com, so that we can do the portal address change, if available.
Note: No special characters allowed in the portal URL.
Can I download an entire folder or do I have to download the image files one at a time?
I am a new user. Wanting to use this with a client (free version). If it works well I will integrate it into my consulting business.
My issues: 1) I am unable to "select" a Client I have set-up. So to add a client user I had to set-up the client again. How do I delete duplicate Clients and why can't I choose a Client I have already set-up? 2) Once I have that all set-up, how do I allow the Client access to the site? 3) What do they have to do to participate? Will they be able to participate fully as a Client user or would I better served to set them up as a project user?
These three items are not discussed on the online help guide that I can find. Thanks, Melinda (ayudaprojects)
@ markander,
As of now, it is not possible to download the entire folder at a time. Instead you can download the image file one at a time.
Hi,
I want to change my email address where i am receiving the mails. Could you please tell me steps about how to change it.
Thanks,
Vishnu
@ vishnukiranreddy,
To change the email address, Login to http://accounts.zoho.com --> click 'My Email IDs' --> click 'Edit' option to the right of the email address --> update the new email address.
Once done all the emails will be received only in your new email address.
I am trying Zoho for the first time & so I may not understand all the possibilities. However, one of the most powerful things in this type of app is the use of task dependencies. It seems I have to have got these worked out in advance and entered tasks not only in the right sequence but also with dates that make dependencies valid.
If I am right, this makes "dependencies" almost unusable. Surely I want to get tasks down as quickly as possible and then specify dependencies. If a "child" task has a start date that is before its newly specified "parent" then the child start date should automatically become the finish date of the "parent". Otherwise I have to use something like MS project to sort things out first and then enter in Zoho .. if so lets just use MSP
Also what happens if I want to add some new Milestone with new dependencies .. do I have to alter all previous stuff manually. Surely not .. it wd be a nightmare. Furthermore, if tasks overrrun, what happens to start dates of "child" tasks; they shd be re-scheduled.
What I would like to be able to do is to fill in task durations only and then the start date of the first task, set the dependencies and then all start & finish dates wd be calculated for me .. wouldn't they?
One further point re Dependencies, can Task Lists be parents & children as per tasks. This can be very useful indeed .. I realise one cd set the last task(chronologically) in a list to be the parent of the first task in another, dependent, list.
Look forward to your comments.
David
How do I ensure that PROJECT TIME VARIANCE be recorded and measured in zohoprojects ?
Specifically, I would like EACH PROJECT broken down INTO TASKS.
Each Task has a specific BUDGETED HOURS (BILLABLE HOURS) - WITH START DATE / FINISH DATE
When I allocate RESOURCES to work on TASKS, while filling up TIMESHEET, ACTUAL EFFORT = BILLABLE HOURS + NON-BILLABLE HOURS (variance)
Can somebody help me with HOW-TO-DO in ZOHOCRM.
~~~~~~~~~~~~~~~
Anil Baddi
www.webmandir.com
Tel +1 630 544 7680
Fax +1 630 214 4949
Is there any way to allocate expenses to a project? Whether they be labor or materials? I would love to have a central place for people to enter their costs. Right now we send by e-mail and it is a data entry pain. Thanks! Mark
How do you see milestones for EVERY project on one screen?
How do we integrate Google Docs & Googles Apps Calendars?
To respond to Barrys' comment, click "My Home" in Zoho projects. It should display all of the milestones assigned to your account.
Now I have a question, is there a way to back-up Zoho projects to a hard drive? I've already solved the problem with Zoho Creator, but the projects post much more of a problem.
We can not see the photos of each other in the project
@Mark+markboylan@aol.com,
As of now, it is not possible to allocate expenses to a project and maintain the total cost of all the project members.
@barrys,
As of now, it's not possible for you integrate Google Docs and Google Apps in Zoho Projects.
Is importing from Microsoft project available in the free version? I can't seem to find where to do it.
@Guest,
Importing Microsoft Project is not possible in current version of Zoho Projects but will be available in the new version of Zoho Projects i.e Zoho Projects 2.0, which will be launched by this month end.
I'd love to be able to establish dependencies within a project template so that they were carried into the newly created project. Is that something that may be available soon? I think your product is great, but that one last feature within the project template would make it even better!
can we link two portals?
I mean I already have some tasks in a portal. but due to some work reasons, i need to perform those tasks in another portal. how can I
move those tasks from the former portal to the new one. thanks
It would be great if there was a built-in chat function like in gmail.
Then we could talk in real time while being on the platform at the same time.
J
when i edit 'company name' of 'edit profile' in 'company settings' menu. 'update profile' button can't update company name column.. help .plz..
@craig,
You can access both the portals (if you are added to the portals) but it's not possible to move tasks from one portal to another portal.
Just getting started evaluating Projects. In setting dependencies, it appears there are the following limitations vs. MS Project
1) dependent task must start on the day following the preceding task, not on the same day,
2) no ability to allow duration of dependent task to overlap part of duration of preceding task,
3) time increments are limited to 1 day, not hours within a day,
I have common situations where several people must report some info and final report is dependent on receipt of all. Actually doing the report happens concurrently with the other people generating their info. Once I have it all, I can finish the report in under an hour.
Can the current Zoho Project handle this and if not, will the 2.o release this month have some or all of these abilities?
Thanks!!
Can i add fields/ pick list to the task form?
Mandar
@mandarmehta,
All the fields in task form are fixed and its not possible to add additional fields to the task form.
@jungbh0830,
Sorry that the profile failed to get updated.
Currently, company & user settings are stored in our central IAM server and the setting changes will reflect after 5 minutes time. This is because of the caching method used in our IAM server.
So, please update profile and check for the changes after 5 minutes of time.
The caching method is not used in Zoho Projects 2.0 (new version of Zoho Projects) and the setting changes will be reflected immediately.
Please can you help?
After I fill in fields in Company Profile at http://japanmusicweek.projects.zoho.com
it says "updated successfully" but returns the previous blank/wrong settings..
jon
@jon,
Currently, company & user settings are stored in our central IAM server and the setting changes will reflect after 5 minutes time. This is because of the caching method used in our IAM server.
So, please update company profile and check for the changes after 5 minutes time.
Note: iSetting changes will be reflected immediately in Zoho Projects 2.0 as the caching method is not used in Zoho Projects 2.0.
i do not know the space fo information collection and where i get all comment of the project
thanks for your help.
Resource Management is a large part of any Project, how is this best acheived...i.e as in MSProject you can see available time, over allocation etc.